A dependency team misses a date that puts your launch at risk. What are your first three actions?
Write your answer first
Saved on this device only — nothing is uploaded.
Reveal model answer & level guide
First, establish the real new date rather than reacting to the miss — a team that slipped once will often slip again, so I want their revised plan and what it is contingent on. Second, work out what it actually costs us: which of our tasks were waiting on it, and whether anything can be resequenced or stubbed so the team is not idle. Third, tell the people who need to replan, with the impact and the options, before they hear it elsewhere. A strong answer does the assessment before the escalation.
- Entry
- Escalate and replan.
- Mid
- Establish the real new date and what it costs you before telling anyone.
- Senior
- Say how you protect the team from idling and who you renegotiate the commitment with.